Ash dykes at Khedar thermal plant threaten villages

Submitted by VK Gupta on Thu, 13/09/2012 - 2:51pm

Ash dykes at Khedar thermal plant threaten villages
September 13, 2012 01:49 PM
By Vinod Gupta
HISSAR: The position of ash dykes at the Khedar thermal plant has become critical and any breach/overflow of water may damage the crops in nearby villages.

As per RTI documents ,Chief Engineer Khedar had informed the Additional Chief Secretary power in July that the position of ash dykes at power station is critical and till now pond ash has been lifted by various agencies. It was also informed that work of construction of roads is in progress in nearby areas and matter has been taken with PWD B&R department for lifting and utilization of pond ash, but in vain.PWD B&R must ensure the mandatory use of wet ash from dykes in their tenders.

The two ash dyke ponds have been filled to capacity in a short period of less than three years. Normally ash content should not be more than 20 % in the water released in dykes but these days water content contained more than 90 % ash leading to complete filling of ash dyke ponds.

According to sources the construction company was to devolve a system where 80 % dry/sold ash was to be collected and remaining 20 % ash was to be merged with water and sent to dykes. But the system has not been made operative till date by the EPC contractor. Against the designed lifting of 6000 ton per day of dry ash500 to 600 ton is being sent to ash silos. The remaining 95 % ash is being pushed to ash dykes with heavy inflow of water. These days the units are not being operated on full load to keep the ash content with in limit. It may be mentioned that Director Technical and a team of engineers from Central Electricity Authority visited the plant earlier this week to assess the critical situation and recommend ways and means to prevent the disaster.

Their report is awaited. Two dykes in 150 acres of land with 7 meters height have been designed for 20 % ash disposal and the same are now being used for 100 % ash disposal. According to sources slurry inflow with high ash contents is 2500 cusecs and discharge has been limited to 1120 cusecs even with the use of third emergency pump. The present critical position has been reached in such a short span against normal period of about 20 years. There is no irrigation or other drain nearby where the water can be released. Previously water was released to the farmers for use in their fields. Now with monsoon rain even farmers are not using any water for last two months.